Prepare the RRP compliance information before the final invoice is sent
Plan the required RRP completion information delivery separately from the firm’s record-retention file.
For a renovation covered by the federal lead-safe renovation rule, the completion file includes information the firm must provide to the relevant recipients. Before sending the final invoice, check the reporting obligation as well as the firm's internal records. Keeping a file in the office and delivering required information are separate tasks.
Section 745.86 sets a timing rule tied to final-invoice delivery or thirty days after completion, whichever is earlier. It identifies the building owner and, where different, the unit occupant among the recipients, with additional provisions for child-occupied facilities. Determine which recipient categories apply to the actual project before closing the administrative file.
Prepare a completion-information checklist with the property and work area, completion date, final-invoice delivery date, assigned certified renovator and the applicable compliance information. Link the supporting work and verification records. The EPA's lead-safe work booklet explains the certified renovator's role, helping the reviewer identify whose project record is relevant.
For example, a firm finishing a covered project may intend to send its final invoice a few days later. Put that planned delivery date beside the completion date and identify the earlier reporting point. Do not assume the firm can always wait until the thirtieth day if it has already delivered the final invoice.
The recordkeeping provision lists applicable documentation such as worker training, containment, waste handling, cleaning and verification. The actual completion report should be prepared from those project facts, not from an unchecked standard statement that every listed practice occurred. If an emergency provision affected compliance, have the responsible person address the required documentation.
Where permitted dust-clearance sampling was used instead of cleaning verification, the rule separately requires provision of the sampling report on the corresponding timing basis. Identify which method actually applies and the resulting document. A general invoice line saying cleaned does not establish that the required report has been supplied.
The firm must retain its compliance records for three years after completion, without displacing longer obligations imposed elsewhere. Keep delivery evidence with the retained file and obtain advice on applicable state, tribal or other requirements. In the site shop, compare project folders, scanners and secure archive supplies for maintaining the completed job record. Select tools that make recipient copies and the firm's retained evidence easy to distinguish and retrieve.
Sources and further reading
- www.ecfr.gov · Read 2026-11-11
- Selected actual federal rule or agency publication · Read 2026-11-11
This is general information. Check the relevant authority or manufacturer for the rules, compatibility and terms that apply to your situation.